PT Sapta Borneo Utama is developing an integrated sugar industry project in Majalengka, West Java, Indonesia consisting of a sugar factory, ethanol facility, biomass power plant and plantation development program.

Key Project Metrics

USD 1.0 Billion Total Project Cost
10,000 TCD Sugar Factory Capacity
315,810 Tons Annual Sugar Production
60 KLPD Ethanol Capacity
30 MW Biomass Power Plant
20 Years Debt Tenor

Project Components

Component Description
Sugar Factory Integrated sugar processing facility with 10,000 TCD capacity.
Ethanol Plant Fuel and industrial ethanol production facility.
Biomass Power Plant Renewable energy generation utilizing bagasse and biomass residues.
Core Plantation 500 hectares plantation development program.
Plasma Program Expansion through 10,000–20,000 hectares farmer partnerships.

Investment Highlights

Financial Highlights

Metric Value
Annual Revenue USD 198.396 Million
EBITDA USD 109.118 Million
CFADS USD 91.712 Million
Annual Debt Service USD 70.548 Million
DSCR 1.30x
LLCR 1.45x
PLCR 1.60x
Project IRR Approx. 11.8%

Project Location

Majalengka Regency, West Java, Indonesia. The site provides access to agricultural resources, industrial infrastructure and long-term expansion potential.

Funding Requirement

Total Project Cost USD 1,000,000,000
Financing Structure Senior Secured Limited-Recourse Project Finance
Debt Facility Up to USD 1,000,000,000
Tenor 20 Years
Interest Rate 3.00% Fixed

Document Information

Document Owner PT Sapta Borneo Utama
Project Integrated Sugar Industry Development Project
Location Majalengka, West Java, Indonesia
Classification Confidential
Status Final / Published
Date June 2026

Revision History

Version Date Document No. Status Description
1.0 June 2026 SBU-PRES-003 Final / Published Executive Summary issued for institutional lender publication.