Infrastructure and utility framework supporting the 10,000 TCD Sugar Mill, 60 KLPD Ethanol Plant, 30 MW Biomass Power Plant and Plantation Program.

Power Infrastructure

ComponentCapacity
Biomass Power Plant30 MW
Steam BoilersBagasse-Fired
Electrical Distribution SystemPlant Wide
Emergency Backup SystemsInstalled

Water & Wastewater Systems

SystemPurpose
Raw Water IntakeIndustrial Water Supply
Water Treatment PlantProcess Water Preparation
Wastewater Treatment PlantEffluent Compliance
Stormwater ManagementDrainage & Flood Control

Storage & Logistics Facilities

FacilityPurpose
Raw Material YardSugarcane Handling
Sugar WarehouseFinished Product Storage
Ethanol Storage TanksProduct Storage
Bagasse Storage AreaBiomass Fuel Storage
Truck Loading AreaInbound & Outbound Logistics

Supporting Infrastructure

Infrastructure Conclusion

The planned utility and infrastructure systems provide adequate support for long-term operation of the integrated industrial complex while meeting environmental, operational and lender technical requirements.